Environmental Permit for a New Inert Landfill
Wardell Armstrong’s Regulatory Support team successfully project managed the preparation of an environmental permit application for a new inert landfill for the client Buffalo Crow, at Hadleigh Quarry in Suffolk.
The multi-disciplinary team led pre-application discussions with the Environment Agency and undertook extensive background monitoring to define the environmental baseline. We prepared a bespoke application including engineering design, operating techniques, waste acceptance, environmental monitoring, financial provision calculations and risk assessments – hydrogeological, stability, amenity and accident.
A bespoke environmental permit was issued in November 2017 and we continue to support the operator to discharge pre-application conditions and report environmental data to the regulator.